Skip Navigation LinksHOME  |  EXPERTISE  |  ENERGY MANAGEMENT  |  ENERGY PERFORMANCE CONTRACTING  |  IRVINGTON
 

ENERGY PERFORMANCE CONTRACTING

 

PROJECTS

IRVINGTON

JAMESTOWN

MARYVALE

Village of Irvington
Energy Performance Contract

client:

Village of Irvington

location:

Irvington, New York

 

Project Scope of Service and Status
The Village of Irvington entered into an agreement with Wendel to perform energy performance improvements and water meter system upgrades throughout the Village on an Energy Performance Contracting basis.

The recommended Facility Improvement Measures at the Village Buildings include:
- High Efficiency Lighting and Controls at
  the Recreation Center, Fire House and
  DPW Complex
- Direct Digital Controls Systems at Village
  Hall, the Recreation Center, Fire House,
  Library and Senior Center
- Overhead Door Replacement at the DPW
  Highway and Sanitation Garages
- Infrared Heaters at the DPW Sanitation
  Garage
- Boiler Replacement at Village Hall, the
  Recreation Center and Fire House
- Window Replacement at Village Hall, the
  Recreation Center and Fire House
- Roof Replacement at the Fire House
- Outside Street Lighting throughout the
  Village
- Building Envelope Improvements at
  Village Hall, the Recreation Center,
  Fire House, Library, Senior Center and
  DPW Complex

The recommended Facility Improvement Measures at the Water District include:
- High Efficiency Lighting and Controls at
  the Pump House
- Building Envelope Improvements at the
  Pump House
- Water Meter Replacement and Installation
  of an AMR System throughout the Village
- Pump Station Upgrades at the Astor
  Street and Ardsley Pump Stations

Energy Use and Costs Prior to Implementation
Consumption: 1,617,548 kWh annually
5,238 mmBtu (fossil fuel) annually
Cost: $341,000 annually

Guaranteed Annual Energy and Cost Savings
Consumption Savings: 394,800 kWh annually
1,833 mmBtu (fossil fuel) annually
Cost Savings: $189,830 annually

Project Status CEA has been completed; Project is currently in design.